GRC
began installing the Signalling System for Taipei's
Mass Rapid Transit (MRT) system in 1990. GRC completed
their scope of work in 2000. GRC's scope included
Tamshui (Red) Line; Hsintien (Green) Line; Chungho
(Orange) Line; Panchiao-NanKang (Blue) Line.
GRC
responsibilities included detail design, equipment
interface coordination, installation, field testing
and maintenance plus numerous project administrative
functions from cost control to materials and warehouse
management. Completion of the above project
demonstrated the capabilities of GRC in the signalling
field.
GRC's
Project Management Capabilities include:
- Detail Design
- Installation
- Scheduling
- Procurement
- Materials Management
- Cost Control
- Quality Assurance and Control
- Interface Coordination
- Field Testing
- Simulation Test
- Maintenance
- Wayside Equipment
- Station Equipment
- Depot Equipment
- Signalling Equipment Room
- EMU Trainborne Equipment
- Central Control Room
-
Training
|